Building 4 Opening Dates
We are thrilled to have Certificates of Occupancy for Building 4 East and West. There are a few more items to complete prior to move in. Claremont is completing the final details in the East building and the West building’s waterproofing has been delayed with the rains but it is 80 % complete. The East …
Building 4 and Nest Update – Aug 10 2022
August 10, 2022For Immediate ReleaseBoard of DirectorsB4 and Nest Update Today we failed our County CO inspection on B4 and the Nest. The County identified new issues that Claremont is addressing now. They will continue to work through the weekend and anticipate completing the work by Sunday evening. If we pass next week, we will …
Building 4 and Nest Update – Aug 5 2022
August 5, 2022For Immediate ReleaseB4 and Nest UpdateHOA Board Your board has been actively engaged in the certificate of occupancy process, working long hours each day to resolve the many obstacles in our path. We always knew the last part of the reconstruction was going to be the most difficult for many reasons. And now …
Nest Update as of 07/28/2022
To: All OwnersFrom: HOA BoardChange to opening dates Due to delays in opening B4, the opening of the Nest is now scheduled for 8/22/2022. Also, it is possible these delays could push everything back an additional week. We will provide updates when we have more information. Wendy BlevinsAssociation [email protected]
Building 4 Failed Inspection – July 25 2022
To: All Owners Building FourFrom: HOA BoardFailed Inspection Today we unexpectedly failed our certificate of occupancy inspection. While we anticipated a few minor issues might arise, we could not predict the County would reverse their sign off on our approved wiring schematics. We passed their electrical inspection, but the department that issues the certificate now …
Building 4 and Nest Update – July 13 2022
Good Afternoon, The Indoor Pool and Exercise room will open on AUGUST 15th. These dates are based on the finish timeline for each building and are not arbitrary. We do not anticipate any changes in these dates but those have become famous last words. If an area is not complete on time, you will be …
Building 4 and Nest Update – July 9 2022
July 9, 2022 We had hoped to receive firm dates this week on completion. However, we have not. Progress is still being made but at a much slower pace than we wanted or expected. The labor shortage is still the biggest issue. At this point we are still anticipating a move in date around the …
Insurance and Construction Update – June 23 2022
June 23, 2022For Immediate ReleaseAll OwnersRE: Insurance and Construction UpdateFrom: Board of Directors Dear Owner, The difficult process of obtaining insurance is now complete. We were able to secure $25M of property, liability, DO and wind insurance for $1,227,876.10. This includes a small charge for interest. The comparable number for insurance in the 2021 budget …
Building 4 and Nest Update – May 27 2022
May 27, 2022FOR IMMEDIATE RELEASEYOUR ATTENTION IS REQUIREDFrom: GSP Board of DirectorsTo: Association Members As we enter the final stages of completion for Building Four and The Nest, we transition from construction to a series of final inspections allowing us to obtain a certificate of occupancy and hurricane insurance. While we are confident we will …